Description of Work:
|
2/28/2018 12:44:58 PM
ORIGINAL SCOPE: Replace of concrete & brick foundation
3/19/2018 10:34:55 AM
REV 02/01/18- Reduce shell area by 100 Sq Ft. Add concrete floor in place of gravel floor. Build out of elevator shaft only. Build foundation for dining room terrace bay approved in DR17-080.
8/7/2018 12:13:22 PM
REVISION 08/03/2018: Level zero interior improvements. Fire sprinklers under sprinkler permit. Addition of Two bathrooms, family room, wine bar. Convenience electrical plans included. Structural scope includes trellis to building attachment. Title 24 Anaylsis dated 26 June 2018. Work approved be the Planning Reso. 2017-20
12/27/2018 11:26:57 AM
approved revised sewer lateral new lateral piping. submitted by contractor Redwood Engineering Rob Poole.
4/1/2019 8:31:36 AM
3-27-19 KH
site visit with Code Enforcement(Gene Diaz), Staff Engineer(Bryant Ho)
discussed activities related to the use of the ROW, employee parking, service vehicle, in the city ROW. Contractor was advised of the parking and traffic related problems that have recently caused residents to complain to city staff.
parking and traffic was addressed with surrounding neighborhood projects at 87 and 94 San Carlos
10/3/2019 10:55:41 AM
7/9/2019 Revision 1 PC1 - submitted for review: Change location of existing and proposed retaining wall between lawn & pool terrace. Add stair along face of retaining wall linking lawn and pool terrace.
an electronic version will be submitted for planning and engineering to review.
Original submittal was entered into the wrong permit (B2016354)
12/30/2019 9:50:00 AM
REVISION: UPDATE PREVIOUS SURFACE CAL. UPDATE RETAINING WALL HEIGHT, REVISED LAND SECTION TO SHOW GARDEN. STRUCTURAL DETAIL CLEAN UP.
|